South Carolina Business Opportunities
Published by Division of Procurement Services - Delbert H. Singleton, Jr., Division Director
Ad Category: Construction
Ad Start Date: October 17, 2018
Agency/Owner: Department of Corrections
Project Name: Deferred Maintenance - Evans CI Cooling Tower and Chiller Replacement
Project Number: N04-9731-FW-A
Construction Cost Range: $675,000 to $850,000
Project Location: Bennettsville, South Carolina
Description of Project/Services:

Demolish existing cooling tower and replace with a two-cell cross flow cooling tower. Demolish and replace one (1) water cooled, 250 ton chiller. Scope includes new concrete piers and steel mounting structure for cooling tower, hydronic piping, electrical, automatic temperature controls, and other Work indicated in the Contract Documents.

Bid/Submittal Due Date & Time: November 14, 2018 - 2:00pm
Number of Bid/Submittal Copies: n/a
Project Delivery Method: n/a
Documents May Be Obtained From: n/a
Project Details: https://scbo.sc.gov/files/scbo/SOSE%20Copier18101618310.pdf
South Carolina Business Opportunities • SCBO Team • 1201 Main Street, Suite 600 • Columbia, SC 29201
803-737-0600 • scbo@mmo.sc.gov • https://scbo.sc.gov • https://procurement.sc.gov
SFAA Logo