Project Name: Macedonia 0.45 MG Elevated Water Storage Tank
Project Number: KCI Project No 00042683_001
Construction Cost Range: $5,500,000
Project Location: Gaffney, SC
Description of Project/Services:
The overall project generally consists of a new 0.45 MG composite elevated water storage tank, demolition of the existing elevated water storage tank, approximately 755 LF of 10” waterline, and associated work tasks for a complete and proper installation.
Bid/Submittal Due Date & Time: January 14, 2025 - 10:00am
Number of Bid/Submittal Copies: 1
Project Delivery Method: Design-Bid-Build
Agency Project Coordinator: KCI Technologies, Inc.
Email: kara.hrkach@kci.com
Telephone: (864) 269-0890
Documents May Be Obtained From: http://www.questcdn.com/
Project Details: https://www.gbpw.com/sites/default/files/2024-12/MacedoniaElevatedWaterStorageTank.pdf