Ad Start Date: January 4, 2019
Agency/Owner: Clemson University
Project Name: Tillman Hall Roof Replacement
Project Number: CUP-4002520
Construction Cost Range: $325,000 - $350,000
Project Location: Clemson Main Campus
Description of Project/Services:

Replacement of the existing metal roof system and installation of a new standing seam metal roof system and flashing on a portion of Tillman Hall.

Bid/Submittal Due Date & Time: February 12, 2019 - 2:00pm
Number of Bid/Submittal Copies: n/a
Project Delivery Method: Design-Bid-Build
Documents May Be Obtained From: n/a
Project Details: https://cufacilities.sites.clemson.edu/capital/projects#2
South Carolina Business Opportunities • SCBO Team • 1201 Main Street, Suite 600 • Columbia, SC 29201
803-737-0600 • scbo@mmo.sc.gov • https://scbo.sc.gov • https://procurement.sc.gov